The yearslong, much-delayed project may be finished by Memorial Day, with pole removal several months out.
Years and many delays after it began, a project to underground power lines in La Jolla Shores is nearing completion, though a specific date is hard to estimate.
The undergrounding project, called Block 1J Phase 1, has been ongoing since January 2020 and will eventually see all utility poles removed as streets are trenched and lines laid underneath in The Shores west of La Jolla Shores Drive from Avenida de la Playa north to UCSD’s Scripps Institution of Oceanography.
San Diego Gas & Electric is performing the work, taking pauses as required by law for the summer construction moratorium, which prohibits roadwork from Memorial to Labor days to ease traffic congestion in busy coastal areas.
The project was scheduled to be completed in late 2023 but has suffered many delays.
Progress is visible, however, as some Shores residents reported at the March 19 La Jolla Shores Association meeting SDG&E crews were pulling lines in their immediate neighborhoods and they had received notices power would be shut off Wednesday, April 2 to transfer to underground lines.
As SDG&E energizes an underground circuit prior to taking power down on various overhead lines, homes will experience an outage of no more than 15 minutes as the underground is connected to each panel, according to SDG&E spokesperson Alex Welling.
The utility company is aiming to complete the underground connections to the new properties before the moratorium cutoff on Memorial Day, Monday, May 26.
If SDG&E is unable to complete every property before the moratorium begins, it will request exemptions on a property-by-property basis to complete the work on private property, Welling said.
Once properties have been switched to the underground circuit, the overhead wires will be removed, and the pole topped, leaving only communication providers on the pole, Welling added.Â
SDG&E and the city of San Diego will coordinate with the various communication providers to remove their facilities from the poles, and then pole removal can begin.
Completion of pole removal is expected now in early 2026.